Amuntay Bridge
It is Located in Brgy. III Dasmarińas Cavite. It is also the fastest route going to the Five Exclusive Subdivision in Brgy. III.
- Project Description
- RMBRCI Using Carbon Fiber Reinforced Polymer (CFRP) for Strengthening of the Bridge
- Retrofitting of Amuntay Bridge
LOCAL BRIDGES - RETROFITTING OF AMUNTAY BRIDGE
Through structural assessment and Detailed Investigation, overall condition of existing structure of the bridge was found out to be in poor state. The Planning and Design Section of the DPWH Cavite 3rd DEO decided for the Retrofitting/Strengthening of the following structure of the bridge.
Location: Dasmarińas, Cavite
Client: DPWH Cavite 3rd District Engineering Office-DEO
Date Started: April 14, 2021
Completion Date: September 20, 2021
- Retrofitting/Strengthening of the following structure of the bridge using Carbon Fiber Sheet (CFS) and Carbon Fiber Plate (CFP) on beam/girder and bottom slab. Carbon Fiber Sheet (CFS) composite material to add strength, last longer and ductility to bridge.
- 1. Removal of loose materials, and Concrete Plaster by means of chipping and grinding.
2. Application of Carbon Fiber Sheet (CFS), and Carbon Fiber Plate (CFP) with Chemical Epoxy resins
3. Restoration of bottom slab, girder and beam on Affected by Carbon Fiber Sheets (CFS), and Carbon Fiber Plate (CFP) Application
4. Protective Coating for concrete Structures (Skim Coat)/ Plastering Works
5. Painting Works (Masonry, and Concrete)