PORTLAMON BRIDGE

Portlamon Bridge is located in Brgy. Portlamon Hinatuan Surigao Del Sur, The bridge is under construction.

  • RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - PORTLAMON BRIDGE

  •  

    After concrete pouring in girder, and dismantling of form works at span 1 to 3. The 1st District Engineering Office - DEO of DPWH was found out that honey comb and spalled concrete on girder. The DPWH 1st District Engineering Office - DEO recommended that the girder of the bridge need to be repair using epoxy putty/mortar and pressurized epoxy on honey comb. 

  •  

    Location: Along Portlamon Hinatuan Surigao Del Sur

    Client: L.C Ting Construction

    Date Started: August 01, 2022

    Completion Date: August 11, 2022

  • To increase the bridge load capacity. The bridge was subject for repair on girder using Epoxy Concrete, and pressurized epoxy on honeycomb, painting works on affected area.
  • 1. Removal of all  Obstructions, and Concrete Plaster by means of chipping and grinding
    2. Patching Works on girder 1, 2,3 & 4 span 1
    3. Crack repair using Epoxy Concrete
    4. Application of protective coating and plastering works
    5. Painting Works on affected areas